Difference between Start\Finish times, Baseline Start\Finish times, and Actual Start\Finish times for project tasks.

Baseline Start\Finish times: Those are the planned times entered during planning to specify the planned start\finish times for each task. Once the plan enters execution, this should not change; however, this remains as a baseline (reference) for comparison with the actual Task Start\Finish times for each task for the purposes of monitoring or evaluation.

Actual Start\Finish times: Those are the actual times periodically entered for each task at the head of its execution and following its completion to specify the actual duration for each task.

Start\Finish times: Those are the forecast-ed times periodically updated for planned tasks to reflect any new inputs which are excepted to change the schedule and which were not foreseen at initial project planning.