The unit for measuring project's work

The answer is Time!

Yes, it is at the first sight a bit surprising since time is used also for scheduling. However, when we mention scheduling, we are more concerned about the task duration with a specific number of resources assigned to complete it.

Take care that!
A specified task duration assigned to a single resource can't be directly halved by assigning it to 2 resources:

This might be an over simplification, as usually this involves at least some interaction between the resources which can add to the communication overhead work to be performed. 